The following sizes are
only indicative and consultations have to be made with SP PowerGrid
for each and every project.
1.1
Maximum Demand less than 1 MVA (850 kW) i.e. single
transformer

1.2
Maximum Demand less than 2MVA
(1700kW) i.e. with 2 nos. 1 MVA transformers

1.3
For
very large widespread sites, SP PowerGrid may agree
to locate the transformers at more than one location, e.g., if 4 transformers
were required, they may agree to have two locations, i.e. one group together
with the Switchgear room and the other group “remote” transformer away from the
switchgear room not more than 200m
1.4
For very large development, SPPG may ask for a 22/6.6 KV
substation at the peripheral of the site with direct access from public road plus 6.6
kV ring main stations within the development. E.g., for Meyer Road Condominium
(3 Blocks, total 460 units), SPPG asked for 1 no. 31 m x 27 m x 5.5 m (H)
22/6.6 KV substation plus 1 no. 12.4 m x 8 m x 3.6 m (H) double ring main
station for each block (size inclusive of Consumer's LV switch room).
2.1
Depth
of main switchboard - use 1.2 m.
2.2
Clearance
at back and sides - allow 0.6 m.
2.3
Clearance
in front with switchgears withdrawn should have at least 0.6 m, for working.
Typically, 1.5 m in front assuming switchgears on withdrawn position will not
exceed 0.9 m.
2.4
Switchboards
may be arranged in one horizontal length, L-shape, or two separate panels facing each other.
2.5
The
basic distribution scheme should be drawn up in order to determine the
switchboard length [such as no. of feeders, generator feeder, essential to
normal changeover, no. of apartment feeders (cable risers or busbar risers), etc.].
2.6
The length of switchboards may be estimated as follows:-
Main Incomer 1000 A to 1600 A - 800 mm
Bus Coupler 1000.A to 1600 A - 800 mm
Branch MCCBs 2 to 3
nos. 400 A to 800 A - 600 mm
Branch MCCBs 3 to 4 nos. 100 to 350 A - 500 mm
ATS 800 A to 1200 A - 800 (W) x 1200 (H)
400 A to 700
A - 600 (W) x 800 (H)
Meter Panel 600 mm x 500 mm
2.7
The headroom of the switchroom
should be taken into consideration whether top entry or bottom entry arrangement.
2.8
Appendix 'A' gives suggested layout of switchrooms.
3.1
Establish
the major essential loads that require standby generator supply, e.g., basement
carpark ventilation, basement sprinklers, lifts , etc.
Estimate the above loads and derive the generator capacity.
3.2
A
summary of the generator capacity of various apartments is given in Appendix 'B'.
3.3
Fuel: In
general, try to install the maximum capacity allowed by FSB in the generator
room (i.e., 1000 litres as stated in SS-532 Storage of
Flammable Liquids), without having to provide fire rated walls around the
tank. Hence, there is no necessity to provide underground storage tank if capacity
is up to 667 KVA, derived as follows:-
1000 litres - 6 hrs
- 0.25 litres/KVA/hr
= 667 KVA
(6 hours as per Clause
11.7 of CP31)
3.4
The
location of the generator room should take into consideration the air Intake
and exhaust and future removal. The most preferred location is on 1st Storey.
|
Layout 1 |
Layout 2 |
|
|
|
|
|
|
|
|
KVA |
|||||
|
150 - 250 |
300 - 400 |
450 - 600 |
750 |
1000 |
1250 |
|
|
A (mm) |
800 |
1000 |
1500 |
1800 |
2000 |
2000 |
|
B (mm) |
2800 |
3200 |
3800 |
4100 |
5000 |
5200 |
|
C (mm) |
1200 |
1300 |
1700 |
1900 |
1900 |
1900 |
|
D (mm) |
700 |
800 |
1200 |
1200 |
1500 |
1500 |
|
E (mm) |
600 |
600 |
700 |
700 |
800 |
800 |
|
F (mm) |
1800 |
1800 |
1800 |
1800 |
1800 |
1800 |
|
G (mm) |
900 |
900 |
900 |
900 |
900 |
900 |
|
Clear Height |
3500 |
3500 |
3800 |
4000 |
4000 |
4000 |
|
Radiator Exhaust Louvre(Gross Area) |
1.5 m2 |
2.5 m2 |
3 m2 |
4 m2 |
5 m2 |
5 m2 |
|
Intake
Louvre (Gross Area) |
4 m2 |
5 m2 |
7.5 m2 |
9 m2 |
10 m2 |
12 m2 |
|
Layout 1 (mm) |
4400 x |
5000 x |
6100 x |
6700 x |
7800 x |
7900 x |
|
Layout 2 (mm) |
5500 x |
6100 x |
7200 x |
7800 x |
8900 x |
9100 x |
|
For Planning, ask
for |
5500 x |
6500 x |
6500 x |
8000 x |
9000 x |
9500 x |
4.1
Basing
on centralized meters, cable risers, and single phase meters for each
apartment.



Appendix
A
A.
Single Feeder with GenSet
A1 Single Line Diagram

A2 Switchboard layout

A3 Switchroom Layout

B. Two Feeders with Genset
B.1 Single Line Diagram
B2 Switchboard Layout

B3 Switchroom Layout

C Single Feeder without Genset

D Double Feeder without Genset

1.1
Generally for load up to 2 MVA, SPPG can
supply at LV. For loads greater than 2 MVA, the supply intake is usually at
22kV.
1.2
For LV
supply, the consumer does not need to invest on HV switchgears and
transformers. However, the tariff is about two times that of HV tariff and more
space will be required at ground floor for SP PowerGrid’s
transformers.. An electrification scheme should be
worked out to determine the cost benefit, if any, for HV supply even though the
load may be less than 2 MVA.
1.3
In some
cases, even though the supply intake is 22 KV, SP PowerGrid
may ask for transformer room(s) adjacent to their switchroom;
this is for their own use (for street lighting, some developments, etc.).
1.4
Typical sizes of SP PowerGrid
22 KV substations are as follows:-
|
Building |
Declared Demand (kW) |
Overall Size (L x W ) |
Remarks |
|
MayBank Building |
|
6.5m x 6.5m |
Special
layout located at 5th Storey |
|
DBS
Building 2 |
7,700 |
10m x 8m |
|
|
Concourse |
6500 |
9.4m x 7.3m |
|
|
Hitachi
Tower |
4,000 |
10m x 7.3m |
|
|
Keppel
Tower |
2,200 |
9.9m x 7.4m
(S/S)+ 3.9m x 4m (T/F) |
*SPPG
requested for a transformer (T/F) room |
|
Phoenix
Tower |
3,000 |
11.6m x
6.6m + 3.9m x 4m (T/F) |
*SPPG
requested for a transformer (T/F) room |
2.1
The
number of feeders for 22 kV supply is usually two (regardless of how low the load). For loads more than 12 MVA,
SPPG may ask for 4 feeders (in which case we need 4 couplers) or even a 66 KV
substation.
2.2
The size of consumers' 22 KV switchroom
can be estimated as follows:-
|
Length |
= |
No. of transformers x 900 mm (AIS) or 600mm (GIS) |
|
|
|
+ |
|
|
|
No. of incoming SPPG feeders x 900 mm (AIS) or 600mm
(GIS) |
|
|
|
+ |
|
|
|
No. of couplers x 1400 mm +
1500 mm (total clearance on both ends) |
|
Width |
= |
5000 mm |
|
Height |
= |
3500mm |
2.3
If there is a possibility of any future additional
transformers, then the length
of the HV switchroom should be increased accordingly.
2.4
The location of the HV switchroom
need not be at the same level as the SPPG substation. However, if the HV Switchroom is at different level, the 22kV Service Cables
will be supplied, installed and maintained by the
customer.
2.5
Doors to the switchroom should
be centrally located, otherwise, two doors should be provided one no. say 1800 (W) x 2400 (H) for
switchgear panels removal and one no. 900 (W) x 2100 (H) for emergency escape.
3.1
Main LV switchrooms should be
located very near or adjacent to the associated transformers to reduce voltage drop and reduce cost of the busbar feeders.
3.2
Typical sizes of LV switchboards are as follows:-
|
|
Gross Area (excluding |
No. of |
|
|
|
Building |
carparks) |
Storeys |
MSBs (WxD) |
EMSBs(WxD) |
|
DBS Building Extension |
65,744 m2 |
37 |
8.6 x 1.2 + 8.2 x 1.2 |
2.2 x 1.0 (750KVA G ) + 2.5x1.0 (750KVA G ) |
|
Concourse |
93,899 m2 |
42 |
6.7 x 1.2 + 5.6 x 1.2 + 8.1 x 1.3 |
3.4 x 1.2 (1250 KVA) + 3.4 x 1.2 (1250 KVA) + 4.2 x 1.2 (1250
KVA) |
|
Hitachi Tower |
45,000 m2 |
37 |
9.5 x 1.2 + 5.3 x 1.2 |
5.3x1.0 (1000KVA G ) +5.3x1.0 (1000KVA G |
|
Phoenix Tower |
25,580 m2 |
23 |
8.8 x 1.0 |
4.7x0.6 (1000KVA G ) |
|
Keppel Tower |
30,000 m2 |
27 |
6.1 x 1.2 + 5.0 x 1.2 |
3.8 x 1.0 (750 KVA G ) 3.8 x 1.0 (750 KVA G ) |
3.3
Two
doors should be provided as per Authority’s requirement; one no. say 1400 (W) x 2100 (H) and one no. 900 (W) x 2100 (H).
3.4
Consider
routing on incoming and outgoing feeders.
3.5
Typical LV Switchroom sizes
a.
2 Feeders and one essential board

ii) 3 feeders and one essential board


5.1
The
location should take into consideration future removal/replacement of the transformer and routing of the incoming and
outgoing feeders.
5.2
A
dividing wall between every two transformers is preferred but not absolutely
essential. The wall is meant to pre-empt possibility of a flashover in one
transformer from affecting the other transformer.
5.3
The
doors should be double leaf of about 2700 (W) x 2700 (H) depending on the size of the
transformer (excluding the housing).
5.4
Limit
the maximum capacity of each transformer to not more than 2500 KVA. Otherwise,
the rupturing capacity of the LV switchboard will be rather high and as such,
not easily available.
5.5
Always
group transformers in pairs. In general, try to size the capacity of each
transformer to cater to 70% of the loads served by both transformers.